Belt conveyor installation
Before installation: After the transfer tower and silo are finished, install the belt conveyor.
Precautions:
All belt conveyors are installed and adjusted according to geological parameters and drawings.
Installation work:
Scribing Check civil construction and view anchor bolts and embedded steel plates
Check the position of each part of the belt conveyor. Install the truss according to the anchor bolt. Installation and adjustment
Equipment (including upper and lower rollers, wipers, drive units, etc.) installation tape hoist installation telescopic head
Install the guide trough mounting tensioner to install all electrical part brackets, tape cutting and vulcanization connections
Work before the end of installation
an examination:
Check that the belt conveyor is consistent with the drawing and geological parameters before installing the tape.
Electrical parts:
Install cable ducts, install limit switches, protection devices, electric control cabinets, etc., install lighting, lay cables,
Connect the wires. Spray paint: Clean the damaged part of the paint and apply spray paint according to the technical specifications.
lubricating oil:
Add grease or lubricant to the following equipment according to the procedure specified in the lubricant operation manual: reducer,
Couplings, cranes, housings, motor bearings, etc. Safety technical measures for the installation of belt conveyors in the main roadway.